The Weak Spot of Infrastructure BCA: Cost Overruns in Seven Road and Railway Construction Projects

Published online by Cambridge University Press:  03 August 2022

Jan-Eric Nilsson*
Affiliation:
Department of Transport Economics, Swedish National Road and Transport Research Institute, SE-581 95Linkoping, Sweden
*
*Corresponding author: e-mail: [email protected]

Abstract

This article describes the process from first proposals in the early 1990s to project completion many years later for seven large Swedish road and railway projects. The purpose is to find reasons for the massive cost overruns as well as explanations for why projects are brought to completion despite much higher costs than when the decision to build was made. Cost overruns are set in an institutional context to highlight the interplay among national, regional, and local policymakers. National investment programs are seen as promises by other parts of society, irrespective of whether project costs increase during the process toward procurement and implementation. Another aspect is that the infrastructure manager’s administrative framework currently makes it impossible to compare costs in contracts with final cost, meaning that there is no institutionalized learning process in place. Design preparations and the estimation of costs for new projects must therefore be done without an understanding of what has been working well in the implementation of previous projects. While Benefit-Cost Analysis (BCA) played no role in the planning of the seven projects, the article sends a stark warning that early cost estimates provide poor input for assessing project rate of return.

Type
Article
Copyright
© The Author(s), 2022. Published by Cambridge University Press on behalf of the Society for Benefit-Cost Analysis

Access options

Get access to the full version of this content by using one of the access options below. (Log in options will check for institutional or personal access. Content may require purchase if you do not have access.)

Article purchase

Temporarily unavailable

References

Andersson, M., Brundell-Freij, K., and Eliasson, J.. 2017. “Validation of Reference Forecasts.” Transportation Research A, 96: 101118.Google Scholar
Andersson, H., Hultkrantz, L., Lindberg, G., and Nilsson, J.-E.. 2018. “Economic Analysis and Investment Priorities in Sweden’s Transport Sector.” Journal of Benefit-Cost Analysis, 9(1): 120146.CrossRefGoogle Scholar
Bajari, P., Houghton, S., and Tadelis, S.. 2014. Bidding for Incomplete Contracts: An Empirical Analysis of Adaptation Costs. American Economic Review, 104(4): 12881319.Google Scholar
Citybanan. 2006. Samhällsekonomisk bedömning av Citybanan och Ytspåret. Transek rapport 2006:61. Bilaga 12 till Ytspårsutredningen Dnr N2006/9955/IR.Google Scholar
Eliasson, J. 2014. “The Role of Attitude Structures, Direct Experience and Framing For Successful Congestion Pricing.” Transportation Research A, 67: 8195.Google Scholar
Eliasson, J., Börjesson, M., van Amelsfort, D., Brundell-Freij, K., and Engelson, L.. 2013. “Accuracy of Congestion Pricing Forecasts.” Transportation Research A, 52: 3446.Google Scholar
Eliasson, J., Börjesson, M., Odeck, J., and Welde, M.. 2015. “Does Benefit–Cost Efficiency Influence Transport Investment Decisions?Journal of Transport Economics and Policy, 49(3): 377396.Google Scholar
Eliasson, J. and Fosgerau, M. 2013. “Cost Overruns and Demand Shortfalls – Deception or Selection? 2013 Transportation Research Part B.” Methodological 57: 105113. https://doi.org/10.1016/j.trb.2013.09.005.Google Scholar
Flyvbjerg, B. 2016. “The Fallacy of Beneficial Ignorance: A Test of Hirschman’s Hiding Hand.” World Development, 84: 176189.CrossRefGoogle Scholar
Flyvbjerg, B. 2021. “Top Ten Behavioral Biases in Project Management: An Overview.” Project Management Journal, 52(6): 531546. https://doi.org/10.1177/87569728211049046.Google Scholar
Flyvbjerg, B., Ansar, A., Budzier, A., Buhl, S., Cantarelli, C., Garbuio, M., Glenting, C., et al. 2018. “Five Things You Should Know about Cost Overrun.” Transportation Research Part A: Policy and Practice, 118: 174190.Google Scholar
Flyvbjerg, B. and Bester, D. W.. 2021. “The Cost-Benefit Fallacy: Why Cost-Benefit Analysis Is Broken and How to Fix It?Journal of Benefit-Cost Analysis, 12: 395419.CrossRefGoogle Scholar
Freedman, J. L. and Fraser, S. C. 1966. “Compliance Without Pressure: The Foot-In-The-Door Technique.” Journal of Personality and Social Psychology, 4(2): 195202. https://doi.org/10.1037/h0023552.CrossRefGoogle ScholarPubMed
Hultkrantz, L., Karlström, U., Nilsson, J.-E. 2008. “The Arlanda Airport Railway Link. Lessons Learned from a Swedish Construction Project.” Review of Network Economics, 7(1): 7794.Google Scholar
Jussila Hammes, J. and Nilsson, J.-E. 2016The Allocation of Transport Infrastructure in Swedish Municipalities: Welfare Maximization. Political Economy or Both?Economics of Transportation, 7: 5364.CrossRefGoogle Scholar
Jäderholm, B. 2020. Stora transportinfrastrukturprojekt– varför blir de försenade och dyrare än vad man räknat med? Beskrivning och analys av sju stora project. [Large transport infrastructure projects - why are they delayed and more expensive than expected? Description and analysis of seven major projects]Google Scholar
Loewenstein, G. and Prelec, D.. 1992. “Anomalies in Intertemporal Choice: Evidence and an Interpretation.” The Quarterly Journal of Economics. 107(2): 573597. https://doi.org/10.2307/2118482. JSTOR 2118482. S2CID 15959172.CrossRefGoogle Scholar
Love, Peter E. D. and Ahiaga-Dagbui, Dominic D.. 2018. “Debunking Fake News in a Post-Truth Era: The Plausible Untruths of Cost Underestimation in Transport Infrastructure Projects.” Transportation Research A: Policy and Practice, 113: 357368.Google Scholar
Malehmir, A., Zhang, F., Dehghannejad, M., Lundberg, E., Döse, C., Friberg, O., Brodic, B., Place, J., Svensson, M., and Möller, H.. 2015. “Planning of Urban Underground Infrastructure Using a Broadband Seismic Land Streamer — Tomography Results and Uncertainty Quantifications From a Case Study in Southwestern Sweden.” Geophysics, 80(6), B177B192. https://doi.org/10.1190/geo2015-0052.1.CrossRefGoogle Scholar
Milgrom, P. and Roberts, J.. 2000. Economics Organization and Management. New Jersey: Prentice Hall.Google Scholar
Molander, P., Nilsson, J.-E., and Schick, A., 2002. Does Anyone Govern? The Relationship Between the Government Office and the Agencies in Sweden. SNS Förlag. Available at https://wwwsnsse.cdn.triggerfish.cloud/uploads/2002/04/does_anyone_govern.pdf (accessed July 01, 2022).Google Scholar
NCHRP. 2020. Traffic Forecasting Accuracy Assessment Research. NCHRP Research Report 934. https://doi.org/10.17226/25637.CrossRefGoogle Scholar
Nellthorp, J. and Mackie, P. J.. 2000. “The UK Roads Review—a hedonic model of decision making.” Transport Policy, 7: 127138.CrossRefGoogle Scholar
Nilsson, J.-E. 1991. “Investment Decisions in a Public Bureaucracy - A Case Study of Swedish Road Planning Practices.” Journal of Transport Economics and Policy, 25: 163175.Google Scholar
Nilsson, J.-E. 2000. Citytunneln. Beslutsprocess och beslutsunderlag. Appendix 3 i Nya vägar till vägar och järnvägar. Underlagsrapport för Riksdagens Revisorer. rapport 2000/01:5.Google Scholar
Nilsson, J.-E. 2002. “Restructuring Sweden’s Railways; The Unintentional Deregulation.” Swedish Economic Policy Review, 9(2), 229254.Google Scholar
Nilsson, J.-E., Ridderstedt, I., and Rushid, A. Ragipi, 2021. Utan spaning. ingen aning. Behovet av data för att följa upp effektivitet. produktivitet och innovationer i anläggningssektorn. VTI rapport 2021:1073.Google Scholar
Reynolds, J. M. 2011. An Introduction to Applied and Environmental Geophysics, 2nd Edn. New York, NY: Wiley Blackwell.Google Scholar
Riksrevisionen. 2010. Kostnadskontroll i stora väginvesteringar? 2010:25.Google Scholar
Riksrevisionen. 2011. Kostnadskontroll i stora järnvägsinvesteringar? 2011:6.Google Scholar
Riksrevisionen. 2012. Underlag och motiv för beslut i två stora infrastrukturobjekt – Västlänken och höghastighetsbanor. RiR 2012:21 – Bilaga 1.Google Scholar
Riksrevisionen. 2021. Kostnadskontroll i infrastrukturinvesteringar. RiR 2021:22.Google Scholar
Riksrevisionsverket RRV. 1994. Infrastrukturinvesteringar – en kostnadsjämförelse mellan plan och utfall i 15 större projekt inom Vägverket och Banverket. Rapport 1994:23.Google Scholar
Salomonsson, J., Nilsson, J.-E., and Nyström, J.. 2019. Sweden Versus Europe in Construction Sector Productivity - A TFP Approach. In 35th Conference of Association of Researchers in Construction Management (ARCOM), Leeds, UK.Google Scholar
Schumpeter, J. 1942. Socialism, Capitalism and Democracy, 3rd Edn. New York: Harper Perennial.Google Scholar
SOU. 1996. 95 Botniabanan.Google Scholar